Alternate Based Question 1:

Sanjay and Tannu working separately can do a piece of work in 6 and 20 days, respectively. If they work for an alternate day, Tannu beginning, in how many days will the work be completed?

  1. 10.5
  2. 8.5
  3. 11.5
  4. 9.5

Answer (Detailed Solution Below)

Option 4 : 9.5

Alternate Based Question 1 Detailed Solution

Given:

Sanjay can do the work in 6 days

Tannu can do the work in 20 days

They work on alternate days starting with Tannu

Formula used:

Work done in 1 day =

Calculation:

LCM of 6 and 20 = 60 units (Assume total work = 60 units)

Sanjay's 1 day work = units

Tannu's 1 day work = units

Work pattern (alternate days starting with Tannu):

Day 1 (Tannu) = 3 units

Day 2 (Sanjay) = 10 units

Total in 2 days = 3 + 10 = 13 units

⇒ In 4 such days (8 days): 13 × 4 = 52 units

Remaining work = 60 − 52 = 8 units

Next day (Day 9, Tannu’s turn): 3 units

⇒ Total = 52 + 3 = 55 units

Next day (Day 10, Sanjay’s turn): 10 units, but only 5 units needed

⇒ Time taken = day

⇒ Total days = 8 + 1 (Tannu) + 0.5 (Sanjay) = 9.5 days

∴ The work will be completed in 9.5 days