Question
Download Solution PDF15 persons have taken a job of digging a pond in 20 days. 5 persons have left after 10 days. Again after 5 days 5 more have left. How many days would be required to complete the job?
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFGIVEN:
Time taken by 15 people to dig the pond = 20 days
FORMULA USED:
Man – day formula
(m1 × d1 × h1)/w1 = (m2 × d2 × h2)/w2
Where m1, m2 is number of persons working
d1, d2 is number of days taken
h1, h2 is number of hours
w1, w2 is the units of work done
CALCULATION:
15 persons have taken a job of digging a pond in 20 days
Total work = 15 × 20 = 300 units
Work done by 15 men in 10 days = 15 × 10 = 150 units
Now,
5 men left the work
Work done by 10 men in 5 days = 10 × 5 = 50 units
Again 5 men left the work
Remaining work = 300 – (150 + 50) = 100 units
⇒ Remaining work will be done in 100/5 = 20 days
∴ Total number of days taken to complete the work = 10 + 5 + 20 = 35 days
Last updated on Jul 18, 2025
-> A total of 1,08,22,423 applications have been received for the RRB Group D Exam 2025.
-> The RRB Group D Exam Date will be announced on the official website. It is expected that the Group D Exam will be conducted in August-September 2025.
-> The RRB Group D Admit Card 2025 will be released 4 days before the exam date.
-> The RRB Group D Recruitment 2025 Notification was released for 32438 vacancies of various level 1 posts like Assistant Pointsman, Track Maintainer (Grade-IV), Assistant, S&T, etc.
-> The minimum educational qualification for RRB Group D Recruitment (Level-1 posts) has been updated to have at least a 10th pass, ITI, or an equivalent qualification, or a NAC granted by the NCVT.
-> Check the latest RRB Group D Syllabus 2025, along with Exam Pattern.
-> The selection of the candidates is based on the CBT, Physical Test, and Document Verification.
-> Prepare for the exam with RRB Group D Previous Year Papers.