Download Solution PDFConcept:
- Critical Path Methods (CPM) have been used for planning scheduling and control in construction project management.
- It is activity oriented method.
Sl. No. | CPM | PERT |
---|---|---|
1. | Critical path method | Program valuation and review technique |
2. | Deterministic | Probabilistic |
3. | Control time and cost | Control only time |
4. | Activity oriented | Event oriented |
5. | One time estimate | Three-time estimate |
6. | Use- Non research | Research |
CPM Network is updated whenever there is a difference in the planned and actual performance.
Last updated on Jun 13, 2025
-> UPPSC AE Mains Exam 2025 registration has been started.
-> UPPSC AE Mains registration window is available till June 27. However, last date to send the documents is July 4.
-> UPPSC AE result 2025 has been released for Prelims exam.
-> UPPSC AE Answer Key 2025 has been uploaded on 23rd April 2025.
-> UPPSC AE Exam was conducted 20th April 2025 on its official website.
-> The UPPSC AE Exam Date 2025 has been released.
-> The Prelims & Mains exam will be conducted on 20th April & 28th September 2025 respectively.
-> A total of 604 vacancies have been released.
-> The applications must be submitted online between 17th December 2024 to 17th January 2025.
-> The selection process includes a written exam, interview, and document verification.
-> Candidates with a BE/B.Tech degree in the relevant discipline, between 21 to 40 years of age are eligible for this post.