Alternate Based MCQ Quiz in मल्याळम - Objective Question with Answer for Alternate Based - സൗജന്യ PDF ഡൗൺലോഡ് ചെയ്യുക

Last updated on Apr 3, 2025

നേടുക Alternate Based ഉത്തരങ്ങളും വിശദമായ പരിഹാരങ്ങളുമുള്ള മൾട്ടിപ്പിൾ ചോയ്സ് ചോദ്യങ്ങൾ (MCQ ക്വിസ്). ഇവ സൗജന്യമായി ഡൗൺലോഡ് ചെയ്യുക Alternate Based MCQ ക്വിസ് പിഡിഎഫ്, ബാങ്കിംഗ്, എസ്എസ്‌സി, റെയിൽവേ, യുപിഎസ്‌സി, സ്റ്റേറ്റ് പിഎസ്‌സി തുടങ്ങിയ നിങ്ങളുടെ വരാനിരിക്കുന്ന പരീക്ഷകൾക്കായി തയ്യാറെടുക്കുക

Latest Alternate Based MCQ Objective Questions

Top Alternate Based MCQ Objective Questions

Alternate Based Question 1:

A tank can be filled by pipe A in 4 hours and pipe B in 6 hours. At 8:00 a.m., pipe A was opened. At what time will the tank be filled if pipe B is opened at 9:00 a.m.?

  1. 10:16 a.m.
  2. 10:22 a.m.
  3. 10:48 a.m.
  4. 10:18 a.m.

Answer (Detailed Solution Below)

Option 3 : 10:48 a.m.

Alternate Based Question 1 Detailed Solution

Given:

Pipe A fills the tank in 4 hours

Pipe B fills the tank in 6 hours

Pipe A is opened at 8:00 a.m.

Pipe B is opened at 9:00 a.m.

Formula used:

Work done by A in 1 hour = 1/4

Work done by B in 1 hour = 1/6

Calculation:

From 8:00 a.m. to 9:00 a.m., only pipe A is working:

⇒ Work done by A in 1 hour = 1/4

From 9:00 a.m. onwards, both pipes A and B are working:

Combined work done by A and B in 1 hour = 1/4 + 1/6 = (3 + 2)/12 = 5/12

Remaining work after 9:00 a.m. = 1 - 1/4 = 3/4

Time taken to complete remaining work = (3/4) / (5/12)

⇒ Time = (3/4) × (12/5) = 9/5 hours = 1.8 hours

1.8 hours = 1 hour and 0.8 × 60 minutes = 1 hour and 48 minutes

Therefore, the tank will be filled at 9:00 a.m. + 1 hour 48 minutes = 10:48 a.m.

∴ The correct answer is option (3).

Alternate Based Question 2:

Pipes A and B can fill a tank in 6 hours and 8 hours, respectively. Both pipes are opened together for 3 hours. After that pipe A is closed, and B continues to fill the tank. In how many hours will the tank be filled?

  1. 2
  2. 4
  3. 3
  4. 6

Answer (Detailed Solution Below)

Option 2 : 4

Alternate Based Question 2 Detailed Solution

Given:

Pipe A can fill the tank in 6 hours.

Pipe B can fill the tank in 8 hours.

Both pipes are opened together for 3 hours, then A is closed and B continues.

Formula Used:

Work done = Time × Rate of work

Calculation:

Rate of work of pipe A = 1/6 (tank/hour)

Rate of work of pipe B = 1/8 (tank/hour)

Work done by both pipes in 3 hours = 3 × (1/6 + 1/8)

\( \frac{1}{6} + \frac{1}{8} = \frac{4 + 3}{24} = \frac{7}{24}\)

Work done by both pipes in 3 hours = 3 × (7/24) = 21/24 = 7/8 (of the tank)

Remaining work = 1 - 7/8 = 1/8 (of the tank)

Time taken by pipe B to fill the remaining 1/8 of the tank = (1/8) / (1/8) = 1 hour

Total time to fill the tank = 3 hours (both pipes) + 1 hour (pipe B) = 4 hours

The tank will be filled in 4 hours.

Shortcut TrickqImage680a122f231d03c030037412

Alternate Method 

Pipe Time to Fill Tank (hours) Efficiency (Tank/hour) Work Done in 3 hours
Pipe A 6 1/6 (1/6) × 3 = 1/2
Pipe B 8 1/8 (1/8) × 3 = 3/8

Total work done by both pipes in 3 hours = 1/2 + 3/8 = 7/8 of the tank.

Remaining work = 1 - 7/8 = 1/8 of the tank.

Time taken by pipe B to fill the remaining 1/8 of the tank = (1/8) ÷ (1/8) = 1 hour.

Total time to fill the tank = 3 hours (both pipes working) + 1 hour (pipe B alone) = 4 hours.

Alternate Based Question 3:

Pipe X can fill a tank in 9 hours and Pipe Y can fill it in 21 hours. If they are opened on alternate hours and Pipe X is opened first, in how many hours shall the tank be full?

  1. \(10 \frac{3}{7}\)
  2. \(12 \frac{3}{7}\)
  3. \(9 \frac{3}{7}\)
  4. \(11 \frac{3}{7}\)

Answer (Detailed Solution Below)

Option 2 : \(12 \frac{3}{7}\)

Alternate Based Question 3 Detailed Solution

Given:

Pipe X fills the tank in 9 hours.

Pipe Y fills the tank in 21 hours.

Pipes are opened alternately, with Pipe X opened first.

Formula used:

Rate of Pipe X = \(\frac{1}{9} \)

Rate of Pipe Y = \(\frac{1}{21} \)

Calculations:

In 2 hours (1 hour by each pipe), the total amount of the tank filled is:

\(\frac{1}{9} + \frac{1}{21}\)

To add these fractions, find the LCM of 9 and 21, which is 63:

\(\frac{1}{9} = \frac{7}{63} and \frac{1}{21} = \frac{3}{63}\)

\(\frac{7}{63} + \frac{3}{63} = \frac{10}{63} \)

In every 2-hour period, \(\frac{10}{63}\) of the tank is filled. Let the total time taken be t hours.

After \(t = 2n \) hours, the total fill will be:

\(\frac{10}{63} \times n \)

We want the tank to be full, i.e., 1 unit of the tank:

\(\frac{10}{63} \times n = 1\)

\(n \) = 63/10 = 6.3 

Therefore, \(t \) = 2n = 2(6.3) = 12.6 hours.

The tank will be full in approximately 12.6 hours, or 12 hours and 36 minutes.

The correct answer is option 2.

Alternate Based Question 4:

A and B alone can do a piece of work in 4 and 9 days, respectively. In how many days will the work be completed, if they both work on alternate days, starting with B? 

  1. \(5\frac{1}{3}\)
  2. \(5\frac{2}{3}\)
  3. 5
  4. \(5\frac{1}{4}\)
  5. None of the above

Answer (Detailed Solution Below)

Option 2 : \(5\frac{2}{3}\)

Alternate Based Question 4 Detailed Solution

Given:

A can do a piece of work = 4 days

B can do a piece of work = 9 days

Formula used:

Total work = efficiency × time

Calculation:

Efficiency Person Time Total work
9 A 4 36
4 B 9

Now,

(B + A) = 4 + 9 = 13 units = 2 days

⇒ (13 × 2) = 26 units =  (2 × 2) = 4 days

⇒ 30 units = 5 days

⇒ 36 units = 5 + (6/9) = 5\(2\over3\) days

∴ The correct answer is 5\(2\over3\) days.

Alternate Based Question 5:

P and Q can complete a piece of work in 28 days and 35 days, respectively. P begins to do the work and they work alternatively one at a time for one day each. In how many days will the whole work be completed?

  1. 18
  2. 31
  3. 21
  4. 27

Answer (Detailed Solution Below)

Option 2 : 31

Alternate Based Question 5 Detailed Solution

Given:

P can complete the work in 28 days.

Q can complete the work in 35 days.

P and Q work alternatively, starting with P.

Formula Used:

1. Work done in 1 day = 1 / Time taken to complete the work.

2. Total work = LCM of individual times.

3. Work completed in 2 days (P and Q working alternatively) = Work done by P in 1 day + Work done by Q in 1 day.

4. Remaining work = Total work - Work completed in full cycles.

Calculation:

LCM(28, 35) = 140 units (Total work).

Work done by P in 1 day = 140/28 = 5 units.

Work done by Q in 1 day = 140/35 = 4 units.

Work done in 2 days (1 cycle of P and Q working alternatively).

Work done in 2 days = 5 + 4 = 9 units.

Number of full cycles = Total work / Work done in 2 days = 140 / 9.

Full cycles = 15 (remaining work will be calculated next).

Work completed in 15 cycles = 15 × 9 = 135 units.

Remaining work = Total work - Work completed = 140 - 135 = 5 units.

On the 31st day, it is P's turn. P can complete 5 units of work in 1 day.

Total days = Days for full cycles + 1 (remaining work).

Total days = (15 × 2) + 1 = 31 days.

The total time required to complete the work is 31 days.

Get Free Access Now
Hot Links: teen patti lotus teen patti yas teen patti download apk teen patti master king