A, B and C can finish a work in 20, 25 and 30 days, respectively. They start working together but B quits after working for 3 days. In how many days from the start shall the work be completed ?

This question was previously asked in
UPSC CAPF AC 2024 Official Paper-I (Held on 4 August 2024)
View all UPSC CAPF AC Papers >
  1. \(9\frac{8}{15}\) days
  2. \(10\frac{1}{15}\) days
  3. \(10\frac{14}{25}\) days
  4. \(11\frac{1}{10}\) days

Answer (Detailed Solution Below)

Option 3 : \(10\frac{14}{25}\) days
Free
UPSC CSE 2025: GS Paper 1 - Mini Live Test
7.6 K Users
30 Questions 60 Marks 35 Mins

Detailed Solution

Download Solution PDF

The Correct answer is Option 3

Key PointsTo solve the problem, we need to calculate the work done by A, B, and C together in the first 3 days, and then determine how much work remains and how long it will take for A and C to finish the remaining work.

Work rate of A:
⇒ A can finish the work in 20 days.
Work rate of A = 1/20 of the work per day.

Work rate of B:
⇒ B can finish the work in 25 days.
Work rate of B = 1/25 of the work per day.

Work rate of C:
⇒ C can finish the work in 30 days.
Work rate of C = 1/30 of the work per day.

⇒ ​The combined work rate of A, B, and C when they work together is: Combined rate = 1/20 + 1/25 + 1/30

⇒ To add these fractions, we find a common denominator (which is 300): 1/20 = 15/300, 1/25 = 12/300, 1/30 = 10/300

⇒ So, Combined rate = 15/300 + 12/300 + 10/300 = 37/300 of the work per day

⇒ In the first 3 days, A, B, and C together complete: Work done in 3 days = Combined rate × Time = (37/300) × 3 = 111/300 of the work

The total work is 1 (whole work), so the remaining work after 3 days is: Remaining work = 1 - 111/300 = 189/300 = 63/100

⇒ Now, A and C will continue to work together. The combined work rate of A and C is: Combined rate of A and C = 1/20 + 1/30

⇒ Finding a common denominator (which is 60): 1/20 = 3/60, 1/30 = 2/60

⇒ So, Combined rate of A and C = 3/60 + 2/60 = 5/60 = 1/12 of the work per day

⇒ To find the time (T) it takes for A and C to finish the remaining 63/100 of the work at the rate of 1/12 of the work per day: T = Remaining work / Combined rate of A and C = (63/100) / (1/12) = (63/100) × 12 = 756/100 = 7.56 days

⇒ ​The total time from the start is the initial 3 days plus the time taken by A and C to finish the remaining work: Total time = 3 + 7.56 = 10.56 days

Thus, the total time from the start when the work is completed is:
10.56 days = 264/25 days

The correct answer is: 3) 264/25 days

 

 

 

 

 

 

 

 

 

Latest UPSC CAPF AC Updates

Last updated on Jun 14, 2025

->The UPSC CAPF AC Merit List is out on the official website. The personality test was held from 5th May to 5th June 2025.

->Earlier, UPSC CAPF AC 2025 Notification had been released. Candidates submitted the detailed application form till 25th March 2025.

-> The Union Public Service Commission (UPSC) has released the notification for the CAPF Assistant Commandants Examination 2025. This examination aims to recruit Assistant Commandants (Group A) in various forces, including the BSF, CRPF, CISF, ITBP, and SSB. 

->The UPSC CAPF AC Notification 2025 has been released for 357 vacancies.

-> The selection process comprises of a Written Exam, Physical Test, and Interview/Personality Test.  

-> Candidates must attempt the UPSC CAPF AC Mock Tests and UPSC CAPF AC Previous Year Papers for better preparation.

Get Free Access Now
Hot Links: teen patti joy teen patti star teen patti master golden india