For a project activity, the optimistic, the pessimistic and the most likely times are 4, 14 and 6 days respectively. Its average time is ________

This question was previously asked in
UGC NET (Management) Official Paper-II (Held On: 12 Mar, 2023 Shift 2)
View all UGC NET Papers >
  1. 10 days
  2. 7 days
  3. 12 days
  4. 9 days

Answer (Detailed Solution Below)

Option 2 : 7 days
Free
UGC NET Paper 1: Held on 21st August 2024 Shift 1
10.8 K Users
50 Questions 100 Marks 60 Mins

Detailed Solution

Download Solution PDF

The correct answer is 7 days.

Key Points To calculate the average time for a project activity using the three-point estimation method, you can use the following formula:

Average Time = (Optimistic Time + 4 * Most Likely Time + Pessimistic Time) / 6

In this case, the optimistic time is 4 days, the pessimistic time is 14 days, and the most likely time is 6 days. Plugging these values into the formula, we get:

Average Time = (4 + 4 * 6 + 14) / 6
Average Time = (4 + 24 + 14) / 6
Average Time = 42 / 6
Average Time = 7

Therefore, the average time for the project activity is 7 days.

Latest UGC NET Updates

Last updated on Jun 12, 2025

-> The UGC NET June 2025 exam will be conducted from 25th to 29th June 2025.

-> The UGC-NET exam takes place for 85 subjects, to determine the eligibility for 'Junior Research Fellowship’ and ‘Assistant Professor’ posts, as well as for PhD. admissions.

-> The exam is conducted bi-annually - in June and December cycles.

-> The exam comprises two papers - Paper I and Paper II. Paper I consists of 50 questions and Paper II consists of 100 questions. 

-> The candidates who are preparing for the exam can check the UGC NET Previous Year Papers and UGC NET Test Series to boost their preparations.

Get Free Access Now
Hot Links: teen patti 50 bonus teen patti master gold teen patti flush