Question
Download Solution PDF30 men can complete a work in 12 days. After 6 days, 24 more men joined them. How many days will they now take to complete the remaining work?
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFGiven:
30 men can complete a work = 12 days
Formula used:
Total work = efficiency × time
Calculation:
Let, the efficiency of a man = M
According to the question:
⇒ (30 × M × 6) + (54 × M × D) = 30 × M × 12
⇒ (54 × M × D) = 30 × M × 6
⇒ D = (30 × 6)/54 = 10/3
⇒ D = 3\(\frac{1}{3}\) days
∴ The correct answer is 3\(\frac{1}{3}\) days.
Last updated on Jul 10, 2025
-> The SSC CGL Application Correction Window Link Live till 11th July. Get the corrections done in your SSC CGL Application Form using the Direct Link.
-> This year, the Staff Selection Commission (SSC) has announced approximately 14,582 vacancies for various Group B and C posts across government departments.
-> The SSC CGL Tier 1 exam is scheduled to take place from 13th to 30th August 2025.
-> Aspirants should visit ssc.gov.in 2025 regularly for updates and ensure timely submission of the CGL exam form.
-> Candidates can refer to the CGL syllabus for a better understanding of the exam structure and pattern.
-> The CGL Eligibility is a bachelor’s degree in any discipline.
-> Candidates selected through the SSC CGL exam will receive an attractive salary. Learn more about the SSC CGL Salary Structure.
-> Attempt SSC CGL Free English Mock Test and SSC CGL Current Affairs Mock Test.