Question
Download Solution PDF40 men can complete a work in 15 days. Three days after they started working, 20 more men joined them. In how many days the total work will be completed?
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFGiven:
40 men can complete work in 15 days
Number of days 40 men worked = 3 days
20 new men are joined
Concept used:
Work = time × efficiency
Calculation:
Let the efficiency of each man be 'm'.
Total work = 40 × m × 15
⇒ 600m
Work done in 3 days = 40 × 3 × m
⇒ 120m
Remaining work = 600m - 120m = 480m
Let the number of days needed to complete the remaining work be N
So, 60 × N × m = 480m
⇒ N = 8
So, total time = 3 + 8
⇒ 11 days
∴ The total work will be completed in 11 days.
Last updated on Jul 12, 2025
-> The SSC CGL Application Correction Window Link Live till 11th July. Get the corrections done in your SSC CGL Application Form using the Direct Link.
-> This year, the Staff Selection Commission (SSC) has announced approximately 14,582 vacancies for various Group B and C posts across government departments.
-> The SSC CGL Tier 1 exam is scheduled to take place from 13th to 30th August 2025.
-> Aspirants should visit ssc.gov.in 2025 regularly for updates and ensure timely submission of the CGL exam form.
-> Candidates can refer to the CGL syllabus for a better understanding of the exam structure and pattern.
-> The CGL Eligibility is a bachelor’s degree in any discipline.
-> Candidates selected through the SSC CGL exam will receive an attractive salary. Learn more about the SSC CGL Salary Structure.
-> Attempt SSC CGL Free English Mock Test and SSC CGL Current Affairs Mock Test.
-> The RRB Railway Teacher Application Status 2025 has been released on its official website.
-> The OTET Admit Card 2025 has been released on its official website.