P and Q together can complete a piece of work in 6 days. If P can alone complete the work in 18 days, then the number of days required for Q to finish the work is:

This question was previously asked in
SSC CGL 2023 Tier-I Official Paper (Held On: 24 Jul 2023 Shift 2)
View all SSC CGL Papers >
  1. 10 days
  2. 8 days
  3. 11 days
  4. 9 days

Answer (Detailed Solution Below)

Option 4 : 9 days
super-pass-live
Free
SSC CGL Tier 1 2025 Full Test - 01
3.3 Lakh Users
100 Questions 200 Marks 60 Mins

Detailed Solution

Download Solution PDF

Given

P and Q together can complete a piece of work in 6 days.

P can alone complete the work in 18 days.

Formula used:

Total work = man × efficiency

Calculation

P’s 1-day work = 1/18

(P + Q)’s 1 day work = 1/6

Q’s 1 day work = 1/6 – 1/18 = 1/9

Hence, Q can alone do the work in 9 days

Shortcut Trick Q’s = [(P + Q) × P] /(P + Q - P)

Q’s = (18 × 6)/(18 - 6)

Q’s = 9 days.

Latest SSC CGL Updates

Last updated on Jul 10, 2025

-> The SSC CGL Application Correction Window Link Live till 11th July. Get the corrections done in your SSC CGL Application Form using the Direct Link.

-> This year, the Staff Selection Commission (SSC) has announced approximately 14,582 vacancies for various Group B and C posts across government departments.

-> The SSC CGL Tier 1 exam is scheduled to take place from 13th to 30th August 2025.

->  Aspirants should visit ssc.gov.in 2025 regularly for updates and ensure timely submission of the CGL exam form.

-> Candidates can refer to the CGL syllabus for a better understanding of the exam structure and pattern.

-> The CGL Eligibility is a bachelor’s degree in any discipline.

-> Candidates selected through the SSC CGL exam will receive an attractive salary. Learn more about the SSC CGL Salary Structure.

-> Attempt SSC CGL Free English Mock Test and SSC CGL Current Affairs Mock Test.

More Work Efficiency Questions

More Time and Work Questions

Get Free Access Now
Hot Links: teen patti tiger teen patti all game teen patti flush