  1. Brown out
  2. Non-cascade tripping
  3. Incipient fault in power transformer
  4. Load shedding

Answer (Detailed Solution Below)

Option 1 : Brown out
Free
Electrical Machine for All AE/JE EE Exams Mock Test
7.9 K Users
20 Questions 20 Marks 20 Mins

Detailed Solution

Download Solution PDF

Brownout triggers the failure of successive parts.

1.) Brownout

  • It refers to a temporary reduction in voltage that directly triggers cascading failures but can affect system performance.
  • Unintentional brownouts can be caused by excessive electricity demand, severe weather events, or a malfunction or error affecting electrical grid control or monitoring systems.
  • Intentional brownouts are used for load reduction in an emergency, or to prevent a total grid power outage due to high demand.
     

2.) Non-cascade tripping

  • Non-cascade tripping refers to a situation where a protective relay or circuit breaker does not operate in a way that isolates a faulted section of the system effectively, leading to the potential for a fault to spread and cause additional failures in other parts of the system. 
     

3.) Incipient fault in power transformer

  • It indicates a developing fault, but it does not immediately lead to the failure of successive parts until it becomes a more serious issue.
  • When the condition of system equipment degrades because of some electrical, thermal or chemical effects, intermittent incipient faults begin to persist in the system.
     

4.) Load shedding

  • Load shedding is a controlled process used to prevent overloading and cascading failures by disconnecting certain loads or areas, so it is a preventive measure rather than a cause of cascading failures.
  • Load shedding aims to prevent a power grid or power source from overloading. As a type of load management, load shedding works by rotating power outages or reducing power consumption from primary sources until demand decreases and more capacity becomes available. 
Latest SSC JE EE Updates

Last updated on Jul 1, 2025

-> SSC JE Electrical 2025 Notification is released on June 30 for the post of Junior Engineer Electrical, Civil & Mechanical.

-> There are a total 1340 No of vacancies have been announced. Categtory wise vacancy distribution will be announced later.

-> Applicants can fill out the SSC JE application form 2025 for Electrical Engineering from June 30 to July 21.

-> SSC JE EE 2025 paper 1 exam will be conducted from October 27 to 31. 

-> Candidates with a degree/diploma in engineering are eligible for this post.

-> The selection process includes Paper I and Paper II online exams, followed by document verification.

-> Prepare for the exam using SSC JE EE Previous Year Papers.

Get Free Access Now
Hot Links: teen patti chart teen patti star apk teen patti rich teen patti gold old version teen patti all game